Supreme Court of Appeal · 14 March 2011

Group Five v Minister of Water Affairs

[2011] ZASCA 17 · case 379/10

CourtSupreme Court of Appeal
Handed downMonday 14 March 2011
Citation[2011] ZASCA 17
Case number379/10
CoramHARMS DP, STREICHER, BRAND, SHONGWE and THERON JJA

In brief

Building Contract – claims for additional payment or compensation – special plea of prescription 2 ___________________________________________________________________

The court's own headnote.

The judgment

The court's own file

THE SUPREME COURT OF APPEAL OF SOUTH AFRICA JUDGMENT Case no: 379/2010 In the matter between: GROUP FIVE CONSTRUCTION (PTY) LIMITED Appellant and THE MINISTER OF WATER AFFAIRS AND FORESTRY Respondent Neutral citation: GROUP FIVE v MINISTER WATER AFFAIRS (379/10) [2011] ZASCA 17 (14 March 2011) Coram: HARMS DP, STREICHER, BRAND, SHONGWE and THERON JJA Heard: 1 MARCH 2011 Delivered: 14 MARCH 2011 SUMMARY: Building Contract – claims for additional payment or compensation – special plea of prescription 2 ___________________________________________________________________ ORDER ___________________________________________________________________ On appeal from: North Gauteng High Court (Pretoria) (Southwood J sitting as court of first instance). The appeal is dismissed with costs including costs of two counsel. ___________________________________________________________________ JUDGMENT ___________________________________________________________________ SHONGWE JA (HARMS DP, STREICHER, BRAND and THERON JJA concurring):

[1]The appellant, Group Five Construction (Pty) Limited, instituted a claim against the respondent, the Minister of Water Affairs and Forestry, for moneys allegedly due in terms of a contract for the construction of the Injaka dam and appurtenant works for the Sabie River Government Water Scheme. Four of the claims arose from claims submitted by the appellant in terms of clause 51 of the contract, which entitled the appellant to claim for additional payment or compensation in prescribed circumstances. The fifth claim, claim E, did not arise for adjudication.

[2]The respondent raised a special plea of prescription and the court below decided to hear this issue separately. The parties placed a list of agreed facts before the court, and led evidence. However, the validity of the special plea depended in the main on an interpretation of the rather complicated contract which had to be read with two amendments agreed to between the parties. These amendments affected clause 61 of the main contract and provided for a new dispute resolution mechanism of submitting disputes to a dispute review board, in lieu of mediation, which was obliged, during the course of the contract, to attempt to settle disputes that arose between the contractor and the employer pursuant to the rejection by the engineer of claims submitted. 3

[3]The amendment provided in summ ary that the board had to make recommendations to the parties. These became final and binding on the parties if they were accepted by them in writing. To the extent that a recommendation was not acceptable in writing by the parties, either party was entitled to refer the unresolved matter to court provided that the particular party had within 60 days, given written notice of its intention to do so. Otherwise the decision of the engineer was to become final and binding.

[4]Therefore the crisp issue between the parties was whether the appellant’s claims, which were the subject of this process, became ‘due’ at the stage when the said written notice was given or whether these claims only became due after completion of the ‘works’ as defined in the contract (as contended by the appellant). The relevance of the issue is to be found in section 12(1) of the Prescription Act 68 of 1969, which provides that prescription commences ‘to run as soon as the debt is due’. It is common cause that if the appellant’s causes of action were ripe and complete when the notices were given these claims had clearly become prescribed.

[5]Southwood J, in a detailed and thorough judgment, reported as Group Five Construction (Pty) Limited v Minister of Water Affairs & Forestry (39161/05) [2010] ZAGPPHC 36 (5 May 2010), came to the conclusion that the claims indeed became prescribed. In spite of a valiant attempt by the appellant’s counsel to convince us otherwise, he missed the point in that he argued that the claims were based on an estimate and consequently represented an advance and not a complete claim ‘of which the debtor is under an obligation to perform immediately’. We are satisfied that Southwood J’s judgment is unassailable and that the argument does not warrant another judgment consisting of the same reasons albeit in different words.

[6]The appeal is dismissed with costs including costs of two counsel. _________________ J SHONGWE JUDGE OF APPEAL 4 APPEARANCES: For Appellant: G D Harpur SC N D Lange Instructed by: Garlicke & Bousfield Inc UMHLANGA ROCKS Claude Reid Inc BLOEMFONTEIN For Respondents: R J Raath SC P M Mtshaulana SC Instructed by: The State Attorney PRETORIA The State Attorney BLOEMFONTEIN